How long did all this take? Atlantis has been more or less steadily
ongoing since the beginning of 1996. This section of the web gives you
some idea of the progress along the way. Although I didn't keep good
records of what was happening in the early days (This was before the web was
popular, remember), store receipts - notably Home Depot - give a pretty clear
picture.
1996 |
|
Early work: Concrete floor plumbing work, two sewage pump
basins. |
1997 |
|
Structural work; Steel beam reinforcement, lally column removal and repositioning.
Rerouting heating ducts
Subfloor leveling and raising, and installing. |
1998 |
|
Drywall finishing.
Bathroom shower floor mud job.
Hardwood (Birdseye maple) floor laying
|
1999 |
|
Staircase
Assorted curves and trim work
Hardwood floor finishing
Glass block wet bar
|
2000 |
|
Pool table
Ceilings
Underwater paintjob
Neon bar shark
Home theater
|
2001 |
|
Boiler Bathroom Drywall
Surprisingly little else |
2002 |
|
|
|